Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 26934 REL 9: 2007-246-00 RESTORATION OF BULL TROUT
Project Number:
Title:
Restoration of Bull Trout Passage at Albeni Falls Dam
Stage:
Implementation
Area:
Province Subbasin %
Intermountain Pend Oreille 100.00%
Contract Number:
26934 REL 9
Contract Title:
2007-246-00 RESTORATION OF BULL TROUT
Contract Continuation:
Previous: Next:
n/a
  • 26934 REL 16: 2007-246-00 EXP RESTORATION OF BULL TROUT PASS
Contract Status:
Closed
Contract Description:
The goal of this project is to provide temporary upstream passage for bull trout at Albeni Falls Dam, Pend Oreille River. We propose to collect bull trout below the dam using a combination of a floating trap that can be positioned at a variety of locations in the tailrace and boat electrofishing. Experiments will be conducted to determine if attraction of bull trout into the trap can be improved by adding bull trout pheromones, water from a bull trout home stream or cold water to the attraction flow from the trap. Trap efficacy will be determined by comparing the number of bull trout caught in the trap to the number caught by electrofishing. Any bull trout captured will be biopsied via hole punch and their DNA sent to the USFWS lab in Abernathy, Washington for rapid analysis within 48 hours. Each DNA sample will be compared to DNA from other bull trout populations in the Priest River drainage, Pend Oreille lake tributaries, and Clark Fork drainage and an assignment will be made as to its probable tributary of origin. The fish will then be transported above Albeni Falls Dam, Cabinet Gorge Dam or other dams without fish ladders, so that they will be able to volitionally migrate into their assigned home tributary, drop back downstream, or migrate upstream to the next dam. Prior to release each fish will be implanted with a combination radio-acoustic transmitter to ascertain if the spawning tributary it selected was the same as its assigned tributary. A system of stationary radio receiving stations and airplane/truck/boat surveys will be used to monitor the movement of the tagged fish. This project provides direct on-the-ground benefits for endangered bull trout in the Pend Oreille Basin because it will allow fish, whose migration corridor has been blocked by a dam without fish passage, to return to their natal streams and contribute their genes (which would otherwise have been lost) to the spawning population.
Account Type(s):
Expense
Contract Start Date:
05/01/2007
Contract End Date:
04/30/2008
Current Contract Value:
$132,863
Expenditures:
$132,863

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Release
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Ensure environmental compliance requirements are complete A: 165. Obtain necessary permits for fish collection and animal handling 05/01/2007 05/01/2007
Install radio tracking receiver ground stations B: 70. Procure, install and test stationary radio receiver stations 11/30/2007 10/05/2007
bull trout released C: 28. Transport bull trout above Albeni Falls Dam 11/10/2007 11/10/2007
Transmitter implantation will be accomplished by PNNL and EWU. D: 158. Implant combination radio acoustic transmitter (CART) into bull trout 11/10/2007 11/10/2007
Weekly electrofishing surveys E: 157. Weekly electrofishing 11/15/2007 11/15/2007
All fixed receiver stations will be inspected and downloaded every other wk (26 times per yr) F: 157. Download stationary ground radio receiving station 12/01/2007 11/21/2007
Track movement of tagged bull trout G: 157. Mobile tracking surveys by fixed wing aircraft, vehicle and boat 12/01/2007 12/01/2007
Develop a profile of each fish tracked H: 162. Data reduction and analysis 01/10/2008 12/20/2007
Funding Package - Submit draft to COTR I: 119. Manage Project 04/30/2008 04/30/2008
Final report uploaded to the BPA website J: 132. Submit Annual Report for the period May 2007 to December 2008 04/28/2008 03/24/2008
Testing of radio receivers L: 70. Calibrate stationary receiver stations prior to spring fieldwork 04/30/2008 04/09/2008

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Trout, Bull (S. confluentus) (Threatened)
  • 1 instance of WE 28 Trap and Haul
  • 2 instances of WE 70 Install Fish Monitoring Equipment
  • 3 instances of WE 157 Collect/Generate/Validate Field and Lab Data
  • 1 instance of WE 158 Mark/Tag Animals
  • 1 instance of WE 162 Analyze/Interpret Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Obtain necessary permits for fish collection and animal handling 02/09/2007
B 70 Procure, install and test stationary radio receiver stations 04/17/2007
C 28 Transport bull trout above Albeni Falls Dam 04/17/2007
D 158 Implant combination radio acoustic transmitter (CART) into bull trout 04/17/2007
E 157 Weekly electrofishing 04/17/2007
F 157 Download stationary ground radio receiving station 04/17/2007
G 157 Mobile tracking surveys by fixed wing aircraft, vehicle and boat 04/17/2007
H 162 Data reduction and analysis 02/09/2007
I 119 Manage Project 02/09/2007
J 132 Submit Annual Report for the period May 2007 to December 2008 02/09/2007
K 185 Periodic Status Reports for BPA 02/09/2007
L 70 Calibrate stationary receiver stations prior to spring fieldwork 12/21/2007